The 175-MVA transformer arrives at Calama wind project site

Engie Chile announced that the 175-MVA transformer has arrived at the site of the Calama wind project in the Chilean region of Antofagasta. The 200-tonne piece of equipment will soon be joined by the first batch of 4.5-MW turbines, which have been unloaded at the port of Angamos. Once all 36 wind turbines are installed, Calama will be able to generate 460 GWh annually. The park is expected to become operational in 2021.

Source: Renewables Now